- This event has passed.
10-11-2017
October 11, 2017
PAVING CREW 1: HELIO, NOE, FRANCISCO, JORGE, MIKE D, KYLER, RONNIE, MIKE L., KEVIN
Wed 6:15am on-site:
job 1: 505 North Main St., Southington, CT (estimator JB) PO#: 3862
— install 400-500 tons of top; binder TBD (install 2 1/2″ of binder, 1 1/2″ top to RED area of plans)
job 2: while in CT—- 5-15 River Rd., Wilton, CT (estimator ) PO#:
— repair ADA areas (Ronnie has picture and knows what needs to be done….)
Plant: Tilcon/New Britain, 642 Black Rock Ave, New Britain (860-224-6010)
____________________________________________________________________________________________
DIG/GRADING CREW: BRIAN, ANTHONY, CARLOS (bobcat) —
Tuesday 5:30pm on-site:
job 1: 505 North Main St., Southington, CT (estimator JB) PO#: 3862
— finish curbing and guardrail repairs, then reclaim 56,000 SF
HOWIE:
Tuesday 9:30pm on-site:
job 1: 505 North Main St., Southington, CT (estimator JB) PO#: 3862
—- (RED area of plans: reclaim heavy duty pavement 14,270 SF) (GREEN area of plans: reclaim standard duty pavement 9,217 SF) total reclaim 23,487 SF —–continue milling total of 169,947 SF
DUMPSITE: Supreme Industries, 49 DePaolo Dr., Southington (contact: Kim, 860-940-1697)
DIG/GRADING CREW2: HELTON, OMAR (need bobcat)
Wednesday 6:30am on-site:
job 1: 27 Page Terrace., Stoughton (estimator CG) PO#: 3424
— exc concrete sidewalk 828 SF. Exc rear asphalt walkway 300 SF.
job 2: 400 A Georgetown Dr. LOT 3, Hyde Park (estimator CG) PO#: 3722
— remove slope granite pieces, exc loam, create new 5 foot wide ramp, 100 SF (make ADA if possible)
_________________________________________________________________________________________________________________________________
PAVING CREW 2: NICK, RICARDO, TONY, ANTHONY, CHRISTIAN, MARCELLO , EDUARDO, JOSE, HELTON
Wed 6:30am on-site:
job 1: 100 Tower St., Hudson (estimator CG) PO#: 2452
— continue paving sidewalks, plus continue the additional work started Tuesday— Additional work: areas are marked out—call Chris Gleeson with questions—-1) Walk repairs bldg. 1 parking lot 175 SF 2) walk by bldg. 2 dumpster 20 SF 3) bldg. 1 berm area R & R 16 LF 4) Bldg 2 berm area by dumpster 15 LF 5) walkway replacement already prepped 15 SF 6) berm by side of office 4 LF 7) maintenance asphalt driveway overlay 8) concrete repairs, cracks and pothole repairs to 3 dumpster pads
____________________________________________________________________________________________________
MILLING CREW: VERNON, JEFF, BILLY, JORDAN, ARTHUR
Wednesday 9PM on-site:
job 1: 50 Ann Mary St. Pawtucket (estimator CG) PO#: 2608 (police detail arrives at 9pm)
—- start mill of 35,381 SF. Make curb reveals a uniform 6″ throughout… (Billy has sketch…)
DUMPSITE: Soullier Sand & Gravel, 100 Huntsbridge Rd., No. Attleboro (Dominic: 508-922-1951) —please call ahead, takes millings at night…17 minutes from jobsite
_____________________________________________________________________________________________________________
OTHER: BOB W., DI, MAURIZIO
Wed 7am on-site:
job 1: 30 Commercial St., Foxboro (estimator PB) PO#: 2606
—- install dry well
__________________________________________________________________________________________
_____________________________________________________________________________________________________________________
SEALCOAT CREW: JOEL, LOUIS
Sealcoat: Job 1 : Louis and Joel
7:30 am onsite: Burlington : 1 Seven Springs Lane ( Get American Sealcoat started )
Then Joel and Louis go to 3 Rehabilitation Way Woburn crackfill approx. 300- 500 lf- See Mark when on site
Then go back to Burlington :
Job 2: Belmont : Belmont Car Wash 521 Trapelo Rd Belmont
Crackfill approx. 1,000 – 1500 lf
__________________________________________________________________________________________________________________________
ATTENTION ALL TRUCK DRIVERS:
THERE WAS AN INCIDENT RECENTLY WHERE ONE OF OUR TRUCK DRIVERS LEFT THEIR BED UP, KNOCKING DOWN WIRES ON A JOB. LUCKILY NOBODY WAS HURT. YOU ARE 100-PERCENT RESPONSIBLE FOR YOUR OWN TRUCKS, MAKING CERTAIN THAT THE BEDS ARE DOWN AND THAT YOU’RE AWARE OF YOUR SURROUNDINGS. PLEASE CHECK YOUR TRUCK BED BEFORE MOVING!!
FOREMEN: PLEASE REMIND YOUR DRIVERS TO MAKE SURE THEIR BODIES ARE DOWN, THAT THEY’RE PAYING ATTENTION ON THE JOB, MAKING SURE THEY’RE WATCHING THEIR SURROUNDINGS AND THE LABORERS.
——————————————————————————————————————————————————————————————————————————————————————————
NOTE: ALL DRIVERS LEAVING FROM THE YARD TO LOAD AT BENEVENTO’S OR KEATING SHOULD ALWAYS TAKE A LOAD OF BROKEN ASPHALT TO DUMP AT THE PLANTS.
——————————————————————————————————–
ALL TRUCKS—–REMEMBER TO TAKE BROKEN ASPHALT FROM YARD, DUMP AT PLANTS WHEN PICKING UP MIX…..!!!!!
—————————————————————————————————
——————————————————————————————————————————————————
KEVIN WAUGH – TRUCK 35 (low bed)
job 1: Wed 5:30am: take bobcat from yard, take to 27 Page Terrace, Stoughton, stay with crew
___________________________________________________________________________________________________________________________________
ROB REARDON – TRUCK 33 (low bed)
job 1: Wed 5am: take piping and drywell from yard, go to 51 Water St., Watertown, get excavator, take all to 30 Commercial St., Foxboro. Then, take mill & water truck from Foxboro, take to 50 Ann Mary St., Pawtucket for Wed PM mill. Then call Nick….
_______________________________________________________________________________________________________________________________
CHRIS HONOR – TRUCK 34
job 1: Wed 5:45am at Keating/Lunenburg, pick up load of top, take to 100 Tower St., Hudson
___________________________________________________________________________________________________________________________________
RUSSELL ROBERTS – TRUCK 37
tonight (Tuesday) 9:30pm on-site: go empty to 30 Commercial St., Foxboro
tomorrow (Wednesday) 9:30pm on-site: go empty to 50 Ann Mary St., Pawtucket
______________________________________________________________________________________________________________________________
KHRIS MARKS – TRUCK 38 (trailer w/bobcat)
tonight (Tuesday) 9pm on-site: go empty to 30 Commercial St., Foxboro
tomorrow (Wednesday) 9pm on-site: go empty to 50 Ann Mary St., Pawtucket
_________________________________________________________________________________________________________________________________
ROB PINTO – TRUCK 32
job 1: Wed 6:15am at Keating/Lunenburg, pick up load of top, take to 100 Tower St., Hudson
____________________________________________________________________________________________
MARIO – TRUCK 36
job 1: 6am at Keating/Lunenburg, pick up load of top, take to 100 Tower St., Hudson
_________________________________________________________________________________________________________________________________
RENTAL TRUCKS:
First Class Rental (617-839-3696)
leave yard at 5:30am with load of stone, take to 600 Canton Ave., Milton, then go empty to 27 Page Terrace, Stoughton
Steve Blackington (603-231-6454)
6am at Keating/Lunenburg, call Pino for info (508-962-5618)….once loaded, go to 11 Independence Way, Bedford
Nick Garofalo (603-303-0446)
tonight (Tuesday) 10pm on-site: go empty to 30 Commercial St., Foxboro
tomorrow (Wednesday) 10pm on-site: go empty to 50 Ann Mary St., Pawtucket
RSL trucking (Alex: 860-982-6932)
6 trucks for Southington, CT for paving, first one at Tilcon, New Britain at 6am
6 trucks for Southington, CT for milling/reclaim, starting at 9:30pm….
MDC (Chris: 508-904-0484)
7am on-site: go empty to 30 Commercial St., Foxboro
____________________________________________________________________________________________________________________
SUBCONTRACTORS
SUB 1: J & J, Milton
–
SUB 2: none
–
SUB 3: none
–
___________________________________________________________________________________________________________________________________
RITACCO BROS DAILY JOBS – PINOT 508-962-5618
EXCAVATION CREW:
7am on site: Hand Work
Somerville: 30 Barton St ( Bill Dunn ) PO# 3388
excavate existing driveway approx. 756 square feet, excavate side of house approx.
240 square feet
Job 2: Brookline: 8 Prince St ( Mike B ) PO# 2813
excavate driveway approx. 1,101 square feet
PAVING CREW:
7am on site:
Bedford: 11 Independence Way ( Bill Rogers) PO# 3323
install binder and top to 1,625 squares feet
Job 2: Bedford: 87 Hartwell Rd ( Bill Rogers) PO# 3517
install binder and top to 1,065 square feet 7am on site:
Job 3 : Repair: Bedford: 7 and 9 Flintlock Drive – Call Rose for details
heat up and repair 1 is ASI repair 1 is Rittaco Bros
Job 4:
Woburn: 17 Third Rd ( Bill Dunn) PO# 3430
install binder and top to 585 square feet and install Binder to apron only at
19 Third Rd
Job 5: Stoneham 40 Hall Road ( Bill Dunn) PO# 3591
install binder and top to 832 square feet
PLEASE MAKE SURE ALL JOBS ARE MEASURED BEFORE YOU START TO DIG.
IF THERE IS ANY DIFFERENCE YOU NEED TO CALL THE ESTIMATOR BEFORE YOU DIG !!!