12-05-2017

December 5, 2017

PAVING CREW 1:     HELIO,  NOE,  , ( MIKE L,  KYLER,  RONNIE,  KEVIN,  EDUARDO, MIKE D,  JORGE  ,  

6:30 am on-site: 

job 1:  22 Front St Fall River ( Chris G )  PO# 3045 

Yellow Area : install stone , grade and  install  top to 4,160 square feet ,

Blue  Area:  install 24  jersery barriers,  forming a box around section that is not being paved

Job 2: 145  Spring St  West Roxbury   ( or you can put 211 Baker St W Roxbury)   Bill  Rogers ( PO# 3578

repair  puddle area  – Call Bill Rogers with any questions

Job 3:  332 Jamaica Way  Jamaica Plain   ( Bill Rogers )

repair puddle area – Call Bill Rogers See  Pic sent  to Ronnie

Job 4:

 

_______________________________________________________________

DIG/GRADING CREW:   BRIAN,- ANTHONY,CARLOS ,  BRING 2-3 BAGS OF CONCRETE WITH YOU 

6:30 on-site:     

8 Mirabeau Lane : Lynnfield , grade approx 8,430 square feet

Job 2: 4  Stoneway  Rd  Lynnfield  ( John B )

install  trench drain at garage door

Job 3: 14 A Crestway Rd , East Boston   ( Mike B )  PO# 5135

excavate existing driveway and front concrete  walkway approx 704 square feet

 

____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

PAVING CREW 2:   TONY , CHRISTIAN,  MARCELLO , Helton   , JOSE   RICARDO,  NICK ( billy has and extra truck call him when your ready  to get mix and he will send one to you 

6:00 am on-site: 

Job 1 250 Rutherford Ave  Charlestown : 

pave approx 24  ton ,  start at front

job 2  8 Mirabeau  Lane : Lynnfield  ( Bill Rogers )  PO# 2075

install  2 ” binder and 1/2″  top to 8,430 square feet

Job 3 : 38 Hillcrest Parkway Winchester:  ( Chris Gleeson) PO # 5168

Fine grade and install  binder only to 2,400 square feet

 

 

 

 

 

___

 

___________________________________________________________________________________________________________________

MILL CREW :   JORDAN,  ARTHUR ,  JEFF,   BILLY , 

6:30  on-site:

81 Willow St Woburn  ( Bill Dun ) PO# 3779

excavate existing driveway 3,558 square feet   ( only 2,300 square feet of this will be paved )

 

Job 2 : 53 Wilson Street  Billerica ( Paul B  ) PO# 5111

excavate tenant driveway and sidewalk in front of whole  house approx 680 square feet

_________________________________________________________________________________________________________________________________

MILL CREW  2: JOEL    VERNON/need  about 12-15 bags of concrete and concrete tools, jackhammer 

 

Job 1:  Norwood;  1064 Pleasant St

repair concrete at FB23  behind the columns , Call Bill Rogers with any questions

 

Job 2:  24 Clapp St  Weymouth, jackhammer  out concrete and  haul away call Chris  Gleeson for details

________________________________________________________________________________________________ 

 

________________________________________________________________________________________________________________________________________________________________________________________________________________________________

SEALCOAT:  Joel – see Mill crew schedule

 

 

 

 

 

 

    _________________________________________________________________________________________________________________________

ATTENTION ALL TRUCK DRIVERS:

THERE WAS AN INCIDENT RECENTLY WHERE ONE OF OUR TRUCK DRIVERS LEFT THEIR BED UP, KNOCKING DOWN WIRES ON A JOB.   LUCKILY NOBODY WAS HURT.  YOU ARE 100-PERCENT RESPONSIBLE FOR YOUR OWN TRUCKS, MAKING CERTAIN THAT THE BEDS ARE DOWN AND THAT YOU’RE AWARE OF YOUR SURROUNDINGS.  PLEASE CHECK YOUR TRUCK BED BEFORE MOVING!!

FOREMEN:    PLEASE REMIND YOUR DRIVERS TO MAKE SURE THEIR BODIES ARE DOWN, THAT THEY’RE PAYING ATTENTION ON THE JOB, MAKING SURE THEY’RE WATCHING THEIR SURROUNDINGS AND THE LABORERS.        

——————————————————————————————————————————————————————————————————————————————————————————

——————————————————————————————————–

ALL TRUCKERS—–REMEMBER TO TAKE BROKEN ASPHALT FROM YARD, DUMP AT PLANTS WHEN PICKING UP MIX…..!!!!!   

—————————————————————————————————

—————————————————————————————————————————–                                                

Kevin B – Trailer dump  

job 1:  8 am on site: empty to Woburn  81 Willow St 

___________________________________________________________________________________________________________________________________

ROB REARDON – TRUCK 33   (low bed)  — 

job 1:  am on site : Helios paving  equipment  to  22 Front St  Fall River, 

then go to   Durastone  150 Higgins Ave Lincoln RI   pick up  24 jersey barriers and take them to  22 Front  St Fall River  

t

CHRIS HONOR – TRUCK 34   

job 1:  5:15 am at Benevento  pick up load of top  going to  22 Front St Fall River 

___________________________________________________________________________________________________________________________________

RUSSELL ROBERTS – TRUCK – first class rental 

job 1:   7 am on site empty to  Woburn 81 Willow St  

 ______________________________________________________________________________________________________________________________

KHRIS MARKS –  TRUCK 38   WITH  bobcat 

job 1: 6:am on site: 81 Willow St Woburn ,  drop  bobcat then  come  back to yard and get trench drain  and a load of stone going to

8 Mirabeau Lane Lynnfield    ( the   drain are for  Brian’s job 2 )

_________________________________________________________________________________________________________________________________

MARIO –  TRUCK 32  

job 1: 7am  on site: Empty to  81 Willow St  (  Nick will call you when  he is ready for you to get mix for Lynnfield job 

____________________________________________________________________________________________

ROB PINTO –  TRUCK 37  

job 1:  5am in  yard  load with a load of stone going to 22 Front St Fall River ( then you will reround to Keating in Acushnet to get mix 

________________________________________________________________________________________________________________________

LOGAN –  TRUCK 36    

job 1:  5:00 am at  Benevento  pick up a load of top going to 250 Rutherford Ave  Charlestown 

_________________________________________________________________________________________________________________________________

RENTAL TRUCKS:

First Class Rental  (Russ:  617-839-3696)(   Russ is  driving  it ) 

 

 

Adam Trucking  (Christian:  781-385-9273)

job 1: 9 am at Benevento  and call  Nick to see what to get for 8 Mirabeau Lane  Lynnfield 

 

 

 

 

 

___________________________________________________________________________________________________________________

SUBCONTRACTORS

SUB 1:  :    

___________________________________________________________________________________________________________________________________

RITACCO BROS DAILY JOBS – PINOT 508-962-5618

PAVE CREW:

7am on site:

Chicopee: 182 Royal St  ( Chris Gleeson ) PO# 5099

Install binder and top to  1,525 square feet

EXCAVATION CREW

7am on site:  Job 1:  Maynard: 151 Main St   (  Mike B ) PO3 3641

saw cut 2 areas approx. 540 square feet

 

Job 2:   Belmont: 56 Oxford Ave  ( Bill Dunn  ) PO# 3142

excavate 700 square feet of dirt and asphalt in 2 locations

(only 356 sf of this area will be paved  )

 

 

 

 

 

 

 

PLEASE MAKE SURE ALL JOBS ARE MEASURED BEFORE YOU START TO DIG.

IF THERE IS ANY DIFFERENCE YOU NEED TO CALL THE ESTIMATOR BEFORE YOU DIG !!!